Change Orders: Why Renovation Budgets Move, and How to Write a Contract That Controls Them

Overruns are not weather. Every one of them was written down at the time, on a piece of paper called a change order.

Budgets do not drift, they get changed

Every renovation that finishes over budget finished over budget for a reason that was written down at the time. That document is the change order. If you understand the four things that generate change orders, and you write a contract that forces each one through a controlled process, you will not eliminate overruns, but you will stop being surprised by them.

The four sources of a change order

1. Unknown conditions

Demolition reveals what the drawings could not: rot at a sill plate, knob and tube wiring in a wall that was supposed to be untouched, a drain line running exactly where the new island goes, a chimney chase nobody knew was there. On a house older than about 1980, assume at least one of these. This is nobody's fault and it is the reason a contingency exists.

2. Owner initiated changes

You see the framed room and decide the window should be a foot wider. Entirely your right, and entirely your cost, and the cost is not just the window. It is the header, the siding patch, the interior trim, the paint, and the two days the framer has to come back.

3. Allowance overruns

The tile you chose costs more than the allowance assumed. These are the most predictable overruns and the easiest to prevent, by making your selections before the contract is signed rather than during construction.

4. Code and inspector driven upgrades

The inspector requires hardwired smoke detectors throughout, or an arc fault breaker, or a larger header than the drawings showed. These are not optional and not negotiable.

What a real change order contains

A text message saying "the extra window will be about two grand" is not a change order. A change order is an amendment to your contract, and it should carry all of the following:

That last point is the whole game. A change order signed after the work is done is not an approval, it is an invoice.

Contract language that actually controls cost

Ask for these clauses before you sign. Most reputable contractors already use some version of them, and the ones who object to all of them are telling you something.

Carry a contingency, and treat it as real money

A reasonable contingency on a cosmetic renovation is about 10 percent. On a gut renovation of an older home, or anything that opens walls and floors, 15 to 20 percent is the honest number. Hold it in your own account, not the contractor's. It is not part of the contract sum, it is your reserve for the change orders you cannot foresee.

The practical test: if a $2,500 unknown condition would force you to stop the job, your budget is not the contract amount, it is the contract amount plus a reserve you do not have.

How to run the process week to week

Set a standing weekly meeting on site, same day and time, with the person who actually directs the crew. Fifteen minutes is usually enough. Three questions:

  1. What was completed since last week, and what is scheduled for next week?
  2. What decisions do you need from me, and by when? Selection delays are one of the largest hidden costs in remodeling, because they idle a crew that is already scheduled.
  3. Is anything on the horizon that could become a change order?

Then follow the meeting with a short email summarizing what was said. You are not building a legal case, you are building a shared record, and a shared record is what keeps a disagreement in month four from becoming a dispute.

When to say no

Not every proposed change deserves approval. Ask what happens if you decline. Sometimes the answer is a genuine code or safety requirement and there is no choice. Often the answer is that the upgrade is nice but optional, and the honest contractor will say so. You are allowed to take three days to decide on anything that is not blocking the crew, and you are allowed to ask for a second price on a large change.

Budgets move on every renovation. The difference between a project that ends at 8 percent over and one that ends at 40 percent over is almost never luck. It is whether every dollar had to walk through a signed piece of paper on its way out.

This article is general information about home renovation, not legal, financial or construction advice. Building codes, licensing rules and lien law differ by state and by city. Confirm anything that affects your project with your local building department and, where money or contracts are involved, with a qualified professional.